Structured Cable Installation
- Installing structured cable from a bulk spool is referred to as pulling cable
- cable must be pulled form the telecommunications closet to the work area
- routed through conduits or wall spaces
- avoids:
- excessive bends
- electrical power cables and fittings
- fluorescent lights
- main fixed cable can be run up to 90 m (295 ft)
- Start at the patch panel:
- label the end of the cable with the jack ID
- run through to work area
- called a drop
- usually drop the cable from the ceiling space to the wall cavity
- leave slack at both ends (service loop)
- cut the cable
- label other end with ID