Structured Cable Installation


  • Installing structured cable from a bulk spool is referred to as pulling cable
    • cable must be pulled form the telecommunications closet to the work area
    • routed through conduits or wall spaces
      • avoids:
        • excessive bends
        • electrical power cables and fittings
        • fluorescent lights
  • main fixed cable can be run up to 90 m (295 ft)
  • Start at the patch panel:
    • label the end of the cable with the jack ID
    • run through to work area
      • called a drop
        • usually drop the cable from the ceiling space to the wall cavity
    • leave slack at both ends (service loop)
    • cut the cable
    • label other end with ID