Work Breakdown Structure (WBS)
Decomposition is a technique for creating the Work Breakdown Structure by subdividing project deliverables to the work package level.
- use to break projects into manageable pieces
Work breakdown structure (WBS) is a highly organized, hierarchical structure, like an organizational chart.
- total project is at the top of the chart
- each level breaks the project down into smaller sections
- one of the first documents you will create in the project planning phase
- uses the deliverables from the project charter as a starting point
- deconstructs them into smaller components until the team understands and estimates them
- feeds into other project documents, such as the project schedule
Key Terms
Task is the action completed to deliver project work.
- not part of the WBS
- include verbs and are things you can do
Activity describes the items you would include in a project schedule.
- project schedule will include a mix of WBS elements, user stories, project tasks, and milestones
Work is the result of doing something, not the act of doing something.
- in WBS, this is a noun
Project schedule includes the WBS deliverables, timing, and resource needs.
- WBS is not a project schedule
- is the starting point
- WBS describes what needs to be delivered
Deliverables are the outcomes of the project.
- observable products, artifacts, and benefits
- every element in the WBS creates a deliverable

Sections of a WBS
- Element
- the deliverables in a WBS
- is each box in a chart and each row in a table
- short, 2-3 words
- details are stored in a WBS dictionary
- Work package
- The smallest, most granular deliverable that is displayed in the lowest-level component of the Work Breakdown Structure
- lowest element in each branch or leg
- element without a child element is a work package
- aka terminal event
- the only level where cost, resources, and timing are estimated
- Level
- layer of the WBS where an element resides
- numbered sequentially, usually starting at level 1,
- which has only one element, the project
- Level 2 has the large deliverables needed to complete the project
- Numbering scheme
- each element is assigned a number according to its place in the hierarchy
- aka code of accounts
- WBS uses a sequential numbering scheme
- each level is separated by a decimal point and restarts at 1
- Leg
- is a group of elements with a shared ancestor
- lowest elements in a leg will roll up to equal everything in the highest level of the leg
- Branch
- one or more elements that do not represent the whole top-level element in the branch