Work Breakdown Structure (WBS)


Decomposition is a technique for creating the Work Breakdown Structure by subdividing project deliverables to the work package level.

  • use to break projects into manageable pieces

Work breakdown structure (WBS) is a highly organized, hierarchical structure, like an organizational chart.

  • total project is at the top of the chart
  • each level breaks the project down into smaller sections
  • one of the first documents you will create in the project planning phase
  • uses the deliverables from the project charter as a starting point
    • deconstructs them into smaller components until the team understands and estimates them
  • feeds into other project documents, such as the project schedule

Key Terms

Task is the action completed to deliver project work.

  • not part of the WBS
  • include verbs and are things you can do

Activity describes the items you would include in a project schedule.

  • project schedule will include a mix of WBS elements, user stories, project tasks, and milestones

Work is the result of doing something, not the act of doing something.

  • in WBS, this is a noun

Project schedule includes the WBS deliverables, timing, and resource needs.

  • WBS is not a project schedule
    • is the starting point
  • WBS describes what needs to be delivered

Deliverables are the outcomes of the project.

  • observable products, artifacts, and benefits
  • every element in the WBS creates a deliverable

Sections of a WBS

  • Element
    • the deliverables in a WBS
    • is each box in a chart and each row in a table
    • short, 2-3 words
      • details are stored in a WBS dictionary
  • Work package
    • The smallest, most granular deliverable that is displayed in the lowest-level component of the Work Breakdown Structure
    • lowest element in each branch or leg
    • element without a child element is a work package
    • aka terminal event
    • the only level where cost, resources, and timing are estimated
  • Level
    • layer of the WBS where an element resides
    • numbered sequentially, usually starting at level 1,
      • which has only one element, the project
    • Level 2 has the large deliverables needed to complete the project
  • Numbering scheme
    • each element is assigned a number according to its place in the hierarchy
    • aka code of accounts
    • WBS uses a sequential numbering scheme
      • each level is separated by a decimal point and restarts at 1
  • Leg
    • is a group of elements with a shared ancestor
    • lowest elements in a leg will roll up to equal everything in the highest level of the leg
  • Branch
    • one or more elements that do not represent the whole top-level element in the branch