Project Baselines
Project baseline an approved time phased plan for a project, a WBS component, a work package, or an activity, plus the approved scope, cost, schedule, and technical changes.
- summarize the scope, cost, and schedule
Types of Baselines
- project baseline consists of 3 parts:
- scope baseline
- describes the need, justification, requirements, and boundaries for the project
- the original scope from the detailed scope statement
- includes the project’s key deliverables
- schedule baseline
- management-approved version of the project schedule
- total project duration captured from the project schedule
- cost baseline
- time-phased budget that will monitor and measure cost performance throughout the project life cycle
- expected costs plus the contingency reserves
- represents the total project cost within the PM’s control
- scope baseline
Benefits
- helps prevent scope creep, cost overruns, and delays
- leads to better estimating and tracking
- aids the change control process
How to Create a Baseline
- Set the scope and key deliverables
- Review the detailed scope statement, and identify the few critical deliverables that set the project’s scope
- Create a schedule with a project duration and deadline
- schedule baseline is the total duration of the project
- Sum the project cost estimate and contingency reserve to create the cost baseline
- total project cost gathered during the resource planning process
- contingency reserve is the total of all contingency calculations you completed during the risk assessment
- Obtain stakeholder approval
- share them with stakeholders to gain buy-in
- baseline is an agreement to the project terms
- can help different areas adjust their expectations
Example
For a project such as a kitchen remodel, the baselines might look like this:
- Scope Baseline: All new appliances (large and small) in matching color scheme; New countertops; New flooring; Painted walls; Tiled backsplash
- Schedule Baseline: 8 weeks
- Cost Baseline: $25,000