Project Baselines


Project baseline an approved time phased plan for a project, a WBS component, a work package, or an activity, plus the approved scope, cost, schedule, and technical changes.

  • summarize the scope, cost, and schedule

Types of Baselines

  • project baseline consists of 3 parts:
    • scope baseline
      • describes the need, justification, requirements, and boundaries for the project
      • the original scope from the detailed scope statement
      • includes the project’s key deliverables
    • schedule baseline
      • management-approved version of the project schedule
      • total project duration captured from the project schedule
    • cost baseline
      • time-phased budget that will monitor and measure cost performance throughout the project life cycle
      • expected costs plus the contingency reserves
      • represents the total project cost within the PM’s control

Benefits

  • helps prevent scope creep, cost overruns, and delays
  • leads to better estimating and tracking
  • aids the change control process

How to Create a Baseline

  1. Set the scope and key deliverables
    • Review the detailed scope statement, and identify the few critical deliverables that set the project’s scope
  2. Create a schedule with a project duration and deadline
    • schedule baseline is the total duration of the project
  3. Sum the project cost estimate and contingency reserve to create the cost baseline
    • total project cost gathered during the resource planning process
    • contingency reserve is the total of all contingency calculations you completed during the risk assessment
  4. Obtain stakeholder approval
    • share them with stakeholders to gain buy-in
    • baseline is an agreement to the project terms
      • can help different areas adjust their expectations

Example

For a project such as a kitchen remodel, the baselines might look like this:

  • Scope Baseline: All new appliances (large and small) in matching color scheme; New countertops; New flooring; Painted walls; Tiled backsplash
  • Schedule Baseline: 8 weeks
  • Cost Baseline: $25,000