Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT) a project network diagram representing duration, activities, and dependencies, including an estimate based on the weighted average duration of activities.
- represents duration, activities, and dependencies
- uses the same diagramming style as PDM
- rectangles for activities and arrows for dependencies
- documents a duration estimate for each activity
- known as the PERT estimate
- is a weighted factor
- requires three duration estimates for each activity:
- Optimistic (O)
- Pessimistic (P)
- Most Likely (M)
- known as the PERT estimate
- PERT estimate weights the most likely value by four against the other values
- formula:
- formula:

- PERT chart adds the PERT estimate to a PND
Example
- Optimistic = 2 days
- Most Likely = 4 days
- Pessimistic = 12 days