Program Evaluation and Review Technique (PERT)


Program Evaluation and Review Technique (PERT) a project network diagram representing duration, activities, and dependencies, including an estimate based on the weighted average duration of activities.

  • represents duration, activities, and dependencies
  • uses the same diagramming style as PDM
    • rectangles for activities and arrows for dependencies
  • documents a duration estimate for each activity
    • known as the PERT estimate
      • is a weighted factor
      • requires three duration estimates for each activity:
        • Optimistic (O)
        • Pessimistic (P)
        • Most Likely (M)
  • PERT estimate weights the most likely value by four against the other values
    • formula:

  • PERT chart adds the PERT estimate to a PND

Example

  • Optimistic = 2 days
  • Most Likely = 4 days
  • Pessimistic = 12 days