Expected Monetary Value (EVM)
Expected monetary value (EVM) is a method of calculating the average outcome when the future is uncertain.
- requires each risk’s probability and impact assessment
- the probability and the financial impact of occurrence are multiplied for each risk
- EMV for each risk is summed to calculate the project’s contingency buffer
- helpful for large, expensive projects with many risks
- formula:
- Applying the formula to each risk generates a list of EMVs, as the following table demonstrates
| Risk | Probability | Impact | EMV |
|---|---|---|---|
| 1 | 5% | -$4,500 | -$225 |
| 2 | 20% | -$1,000 | -$200 |
| 3 | 30% | -$20,000 | -$6,000 |
| 4 | 15% | -$15,000 | -$2,250 |
| 5 | 50% | -$5,000 | -$2,500 |
| Total EMV: | -$11,175 | ||
| Contingency Reserve: | $11,175 |