Estimation Techniques
Estimation is the process of assigning a forecasted value to an activity’s duration, effort, or cost.
Top-Down Estimating
Top-down estimating is an estimation technique encompassing the entire project or its key deliverables, and which cascades estimates down to the activity level.
- creates an estimate of the entire project or key deliverables
- Then estimates are cascaded down to the activities
- less accurate than other techniques
- works well when you don’t have more information
Bottom-Up Estimating
Bottom-up estimating is a method of estimating the cost for each work package in the work breakdown structure (WBS). The estimates are then rolled up or aggregated for progressively higher levels within the WBS.
- creates estimates at the lowest-level activities, work packages, and user stories
- Then, the individual estimates are added together to create a project estimate
- more time consuming but more accurate than a top-down estimate
Analogous Estimating
Analogous estimating is a top-down estimating technique using duration of previous similar activities to estimate future duration.
- uses historical data
Parametric Estimating
Parametric estimating is a technique that is used to predict total project costs by using the project’s characteristics and historical information in a mathematical model.
- augments either bottom-up or top-down estimates with historical data
- uses known variables, such as cost per hour and the number of hours, to create a custom estimate for a project
Three-Point Estimating
Three-point estimating is a method of activity duration estimating in which three types of estimates are incorporated into a singular duration estimate scenario: most likely, optimistic, and pessimistic.
- factors in multiple scenarios and creates an average estimate
- for each estimate, you collect three values:
- Optimistic (O)
- The estimate if everything happens perfectly
- Most likely (M)
- estimate of the most likely outcome
- will be somewhere between optimistic and pessimistic
- Pessimistic (P)
- estimate if everything goes wrong
- Optimistic (O)
- Formula: