Estimation Techniques


Estimation is the process of assigning a forecasted value to an activity’s duration, effort, or cost.

Top-Down Estimating

Top-down estimating is an estimation technique encompassing the entire project or its key deliverables, and which cascades estimates down to the activity level.

  • creates an estimate of the entire project or key deliverables
  • Then estimates are cascaded down to the activities
  • less accurate than other techniques
  • works well when you don’t have more information

Bottom-Up Estimating

Bottom-up estimating is a method of estimating the cost for each work package in the work breakdown structure (WBS). The estimates are then rolled up or aggregated for progressively higher levels within the WBS.

  • creates estimates at the lowest-level activities, work packages, and user stories
  • Then, the individual estimates are added together to create a project estimate
  • more time consuming but more accurate than a top-down estimate

Analogous Estimating

Analogous estimating is a top-down estimating technique using duration of previous similar activities to estimate future duration.

  • uses historical data

Parametric Estimating

Parametric estimating is a technique that is used to predict total project costs by using the project’s characteristics and historical information in a mathematical model.

  • augments either bottom-up or top-down estimates with historical data
  • uses known variables, such as cost per hour and the number of hours, to create a custom estimate for a project

Three-Point Estimating

Three-point estimating is a method of activity duration estimating in which three types of estimates are incorporated into a singular duration estimate scenario: most likely, optimistic, and pessimistic.

  • factors in multiple scenarios and creates an average estimate
  • for each estimate, you collect three values:
    • Optimistic (O)
      • The estimate if everything happens perfectly
    • Most likely (M)
      • estimate of the most likely outcome
      • will be somewhere between optimistic and pessimistic
    • Pessimistic (P)
      • estimate if everything goes wrong
  • Formula: