Earned Value Management
Earned value management (EVM) is a methodology that measures project progress by comparing actual schedule and cost performance against planned performance as laid out in the schedule and cost baselines.
- uses three values to monitor schedule and cost performance:
- Planned Value (PV)
- target cost and schedule
- Earned Value (EV)
- actual schedule
- Actual Cost (AC)
- actual cost
- Planned Value (PV)
- PV, EV, AC are point-in-time values
- EVM chart looks much like a burnup chart


Calculating the Base EVM Metrics
Budget at completion (BAC) is the total budgeted cost of the project at completion.
Planned value (PV) is the cost allocated to a specific amount of work.
- formula:
- e.g., PV estimates that 10% of the project’s work should use 10% of the project budget
Earned value (EV) is how much of the project’s work was delivered within a specific period.
- represents how much of the project’s scheduled work is actually completed
- formula:
- Actual cost (AC) equals the actual project cost up to a particular time
Cost Performance Metrics
Cost Variance
Cost variance (CV) is the difference between the EV and the AC incurred to complete that work.
- compares what the delivered work is worth against what it costs
- Positive CV mean project is under budget
- formula:
- results:
- CV > $0
- project is spending less money than expected
- CV = $0
- project is spending exactly as much as expected
- CV < $0
- project is spending more money than expected
- CV > $0
- e.g., EV = 100, AC = 50, CV = 100 - 50 = 50
- project spent $50 less than expected so far
Cost Performance Index
Cost performance index (CPI) is a measurement of cost performance that is used to determine whether the project is over or under budget.
- divides EV by AC to create a ratio
- formula:
- results:
- CPI > 1
- project is spending less money than expected
- CPI = 1
- project is spending exactly as much as expected
- CPI < 1
- project is spending more money than expected
- CPI > 1
Schedule Performance Metrics
- same as cost but for schedule
Forecasting Performance
- estimate at completion (EAC)
- bottom-up
- variance at completion (VAC)