Earned Value Management


Earned value management (EVM) is a methodology that measures project progress by comparing actual schedule and cost performance against planned performance as laid out in the schedule and cost baselines.

  • uses three values to monitor schedule and cost performance:
    • Planned Value (PV)
      • target cost and schedule
    • Earned Value (EV)
      • actual schedule
    • Actual Cost (AC)
      • actual cost
  • PV, EV, AC are point-in-time values
  • EVM chart looks much like a burnup chart

Calculating the Base EVM Metrics

Budget at completion (BAC) is the total budgeted cost of the project at completion.

Planned value (PV) is the cost allocated to a specific amount of work.

  • formula:
  • e.g., PV estimates that 10% of the project’s work should use 10% of the project budget

Earned value (EV) is how much of the project’s work was delivered within a specific period.

  • represents how much of the project’s scheduled work is actually completed
  • formula:
  • Actual cost (AC) equals the actual project cost up to a particular time

Cost Performance Metrics

Cost Variance

Cost variance (CV) is the difference between the EV and the AC incurred to complete that work.

  • compares what the delivered work is worth against what it costs
  • Positive CV mean project is under budget
  • formula:
  • results:
    • CV > $0
      • project is spending less money than expected
    • CV = $0
      • project is spending exactly as much as expected
    • CV < $0
      • project is spending more money than expected
  • e.g., EV = 100, AC = 50, CV = 100 - 50 = 50
    • project spent $50 less than expected so far

Cost Performance Index

Cost performance index (CPI) is a measurement of cost performance that is used to determine whether the project is over or under budget.

  • divides EV by AC to create a ratio
  • formula:
  • results:
    • CPI > 1
      • project is spending less money than expected
    • CPI = 1
      • project is spending exactly as much as expected
    • CPI < 1
      • project is spending more money than expected

Schedule Performance Metrics

  • same as cost but for schedule

Forecasting Performance

  • estimate at completion (EAC)
  • bottom-up
  • variance at completion (VAC)