Dependencies and Sequencing
Dependency is a logical relationship that exists between two project activities.
- If two activities have a dependent relationship,
- one activity cannot start or finish until the other activity starts or finishes
- control the order of events in a project
- can visualize dependencies in multiple ways
- project schedule lists the predecessors for each dependency
- Gantt charts and project network diagrams show arrows connecting dependent activities.
Project network diagram is a graphical representation of the sequence of project activities and the dependencies among them.

Dependency Sequencing
- Finish-to-Start (FS)
- precedence relationship between two activities where the predecessor activity must finish before the successor activity can start
- most common dependency type
- Activity A must finish before Activity B can begin
- Start-to-Start (SS)
- precedence relationship between two activities where the predecessor activity must start before the successor activity can start
- Activity A must start before Activity B can start
- Finish-to-Finish (FF)
- precedence relationship between two activities where the predecessor activity must finish before the successor activity can finish
- Activity A must finish before Activity B can finish
- Start-to-Finish (SF)
- precedence relationship between two activities where the predecessor activity must start before the successor activity can finish
- Activity A must start before Activity B can finish
- rarest type