Dependencies and Sequencing


Dependency is a logical relationship that exists between two project activities.

  •  If two activities have a dependent relationship,
    • one activity cannot start or finish until the other activity starts or finishes
  • control the order of events in a project
  • can visualize dependencies in multiple ways
    • project schedule lists the predecessors for each dependency
    • Gantt charts and project network diagrams show arrows connecting dependent activities.

Project network diagram is a graphical representation of the sequence of project activities and the dependencies among them.

Dependency Sequencing

  • Finish-to-Start (FS)
    • precedence relationship between two activities where the predecessor activity must finish before the successor activity can start
    • most common dependency type
    • Activity A must finish before Activity B can begin
  • Start-to-Start (SS)
    • precedence relationship between two activities where the predecessor activity must start before the successor activity can start
    • Activity A must start before Activity B can start
  • Finish-to-Finish (FF)
    • precedence relationship between two activities where the predecessor activity must finish before the successor activity can finish
    • Activity A must finish before Activity B can finish
  • Start-to-Finish (SF)
    • precedence relationship between two activities where the predecessor activity must start before the successor activity can finish
    • Activity A must start before Activity B can finish
    • rarest type