Cost-Plus Contracts


Cost-plus contract is a contract type that provides vendors a refund of the expenses incurred while providing a service, plus a fee representing vendor profit.

  • aka cost-reimbursable contract
  • pays for all resource costs needed to complete the work plus a fee to the vendor
    • fee represents the vendor’s profit margin
  • places most of the risk on the buyer

Types

  • cost-plus fixed fee (CPFF)
  • cost-plus incentive fee (CPIF)
  • cost-plus award fee (CPAF)
  • cost-plus percentage of cost (CPPC)

Cost-Plus Fixed Fee (CPFF)

Cost-plus fixed fee (CPFF) is a cost-reimbursable contract that ensures that the vendor is reimbursed for all allowable costs for performing the work; the vendor receives a fixed fee payment based on the initial estimated project costs.

  • vendor receives a fixed fee for the work
  • fee will not change if the scope, costs, or performance changes
  • appealing to vendors when a project is otherwise unattractive

Cost-Plus Incentive Fee (CPIF)

Cost-plus incentive fee (CPIF) is a cost-reimbursable contract that ensures that the vendor is reimbursed for all allowable costs for performing the work; the vendor also receives a predetermined target fee and an incentive fee.

  • builds incentives into the fee structure
  • e.g., standard CPIF model is to give the vendor a portion of the savings when a project is completed under budget
  • incentivizes the vendor to control costs
  • reduces risk for the buyer
  • increases risk for the vendor
    • vendor will receive a larger payout for the increased risk

Cost-Plus Award Fee (CPAF)

Cost-plus award fee (CPAF) is a cost-reimbursable contract that ensures that the vendor is reimbursed for all legitimate costs; the majority of the fee is earned based on satisfying certain broad subjective performance criteria defined and incorporated into the contract.

  • pays costs plus a fee adjusted for performance
  • includes performance goals in the contract
    • goals are not easily measurable
    • organization subjectively assesses the vendor’s performance and adjusts the fee accordingly
    • If the vendor fails to meet expectations, they will not receive payment
  • payment awarded is not open to negotiation

Cost-Plus Percentage of Cost (CPPC)

Cost-plus percentage of cost (CPPC) is a cost-reimbursable contract that ensures that the vendor is reimbursed for all allowable costs for performing the work and a fee equal to a percentage of all costs.

  • vendor receives a fee equal to a percentage of all costs
  • vendor prefers this type of contract for
    • high-value projects
    • projects where predicting a final cost is difficult
  • contains no total cost, which increases risk for buyers
  • Buyers prefer this contract when costs are well understood and under control
    • benefits buyers when they want to focus on other elements, such as performance or quality