Assign Resources
- The resource assignment process includes two activities:
- Assign RACI roles via a RAM
- Assign human and physical resources via a project scheduling tool
Responsibility Assignment Matrix (RAM)
A responsibility assignment matrix (RAM) is a chart that links key project stakeholders to specific project deliverables or activities by assigning responsibilities to each stakeholder for each element of work.
- started in the project initiation phase and populated with team members and roles
- uses four roles:
- Responsible (R)
- The person who will do the work
- Accountable (A)
- The person who will be held accountable for the final work
- Consulted (C)
- The person who can offer expertise on the work but will not work on it directly
- Informed (I)
- The person who needs to know when the work is done
- Responsible (R)
Project Schedule Assignments
- need to consume resources through a project management scheduling tool
- scheduling software will include a list of project activities, dependencies, milestones, and dates
- process
- For each task, assign the physical resources used or consumed
- Next, select the people who will be actively working on the task
- the people responsible for the task on the Gantt chart
- process is called resource loading
- The process of assigning work to a person until all their available capacity is consumed
Project Schedule
A project schedule is the project team’s plan for starting and finishing activities on specific dates and in a certain sequence.
- specifies planned dates for meeting project milestones
- includes the project timeline, resources used, due dates, and dependencies