Assign Resources


  • The resource assignment process includes two activities:
    1. Assign RACI roles via a RAM
    2. Assign human and physical resources via a project scheduling tool

Responsibility Assignment Matrix (RAM)

A responsibility assignment matrix (RAM) is a chart that links key project stakeholders to specific project deliverables or activities by assigning responsibilities to each stakeholder for each element of work.

  • started in the project initiation phase and populated with team members and roles
  • uses four roles:
    • Responsible (R)
      • The person who will do the work
    • Accountable (A)
      • The person who will be held accountable for the final work
    • Consulted (C)
      • The person who can offer expertise on the work but will not work on it directly
    • Informed (I)
      • The person who needs to know when the work is done

Project Schedule Assignments

  • need to consume resources through a project management scheduling tool
  • scheduling software will include a list of project activities, dependencies, milestones, and dates
  • process
    • For each task, assign the physical resources used or consumed
    • Next, select the people who will be actively working on the task
      • the people responsible for the task on the Gantt chart
      • process is called resource loading
        • The process of assigning work to a person until all their available capacity is consumed

Project Schedule

A project schedule is the project team’s plan for starting and finishing activities on specific dates and in a certain sequence.

  • specifies planned dates for meeting project milestones
  • includes the project timeline, resources used, due dates, and dependencies